How firms decide which long-term projects to fund, and how those decisions connect to bank term lending. This guide covers Non-Discounted methods (Payback, ARR), Discounted Cash Flow methods (NPV, IRR, PI), Deferred Payment Guarantee, Project Financing, and Term Loan Appraisal vs Project Appraisal — with a free NPV/Payback calculator and 50 exam-style MCQs with hidden answers.
📅 Updated: September 2026 • 28 min read
1 Non-Discounted Cash Flow Methods
Payback Period = Initial Investment ÷ Annual Cash Inflow
(for even cash flows) — the time taken to recover the initial outlay
ARR = Average Annual Profit ÷ Average Investment × 100
Uses accounting profit, not cash flow
JAIIB tip: Both Payback Period and ARR ignore the time value of money — a rupee received in Year 1 is treated identically to a rupee received in Year 5. Payback also ignores all cash flows occurring after the payback point.
2 Discounted Cash Flow Methods
Net Present Value (NPV)
PV of cash inflows minus initial investment, discounted at cost of capital. Accept if NPV > 0.
Internal Rate of Return (IRR)
The discount rate at which NPV = 0. Accept if IRR > cost of capital/hurdle rate.
Profitability Index (PI)
PV of Cash Inflows ÷ Initial Investment. Accept if PI > 1 — especially useful for ranking projects under capital rationing.
3 Comparing NPV and IRR
Aspect
NPV
IRR
Reinvestment Assumption
Reinvests interim cash flows at the cost of capital — more realistic
Reinvests at the IRR itself — can be unrealistic for very high-IRR projects
Mutually Exclusive Projects
Generally the superior ranking method
Can conflict with NPV rankings in some scenarios
Non-Conventional Cash Flows
Always gives one clear answer
May yield multiple or no real IRR solutions
JAIIB tip: Where NPV and IRR give conflicting rankings for mutually exclusive projects, NPV is generally preferred, since its reinvestment assumption (at cost of capital) is more realistic than IRR's.
4 Basic Concepts of Term Loans
A Term Loan is a loan sanctioned for a fixed period, typically to finance capital expenditure or a project, and repaid via a fixed instalment schedule out of the borrower's future cash accruals. The key appraisal metric is DSCR (Debt Service Coverage Ratio), and the loan is typically structured with a moratorium period before regular repayment begins.
Deeper dive: This topic is covered in full depth — including all major types of term loans, DSCR calculation, and a free DSCR/EMI calculator — in our dedicated Term Loan Assessment guide.
5 Deferred Payment Guarantee (DPG)
🤝
Definition
A Deferred Payment Guarantee (DPG) is a bank guarantee issued on behalf of a buyer to a seller, guaranteeing payment of deferred instalments for capital goods purchased on credit — functioning like a term loan, but structured as a contingent liability (guarantee) rather than direct fund-based lending.
The bank earns a commission (rather than interest) on a DPG, though the seller typically builds an interest cost into the deferred instalment price. DPGs are especially common for financing machinery purchases.
6 Project Financing
🏗️
Definition
Project Financing structures a loan around the cash flows and assets of a specific project — often via a dedicated Special Purpose Vehicle (SPV) — rather than the sponsor's overall balance sheet strength.
Because the lender's recourse is limited mainly to the project's own assets and cash flows, this is called non-recourse or limited-recourse financing — the dominant structure for large infrastructure projects like roads, power plants and ports.
7 Term Loan Appraisal vs Project Appraisal
Aspect
Term Loan Appraisal
Project Appraisal
Typical Borrower
Existing, operational business seeking capex/expansion finance
New project, often Greenfield, via SPV/project financing
Track Record
Existing operations provide a track record to lean on
No track record — appraisal is entirely projection-based
Rigor of Feasibility Study
Moderate, focused on incremental project cash flows
Comprehensive — technical, market, financial and managerial feasibility studied in depth
🧮 NPV & Payback Calculator
Enter your initial investment, discount rate, tenure, and expected even annual cash inflow.
Project Details
Results
Payback Period—
PV of Cash Inflows—
Net Present Value (NPV)—
Profitability Index (PI)—
Assumes even annual cash inflows for simplicity.
✓ Key Takeaways
Payback Period and ARR ignore the time value of money; NPV, IRR and PI discount future cash flows.
NPV is generally the superior method for ranking mutually exclusive projects, thanks to its more realistic reinvestment assumption.
A DPG functions like a term loan but is structured as a bank guarantee (contingent liability), earning commission rather than interest.
Project Financing via an SPV is typically non-recourse/limited-recourse, relying on the project's own cash flows rather than the sponsor's balance sheet.
Project Appraisal for a new/Greenfield venture is far more rigorous than Term Loan Appraisal for an existing business, since there is no operating track record to lean on.
📝 Top 50 JAIIB-Style MCQs on Capital Investment Decisions & Term Loans
Test your understanding with these 50 practice MCQs, closely modelled on the pattern expected in the JAIIB AFM exam — including combination-answer questions. Each question has 5 options — the correct answer is hidden by default; tap "Show Answer" to reveal it along with a short explanation.
⏱️ Non-Discounted Cash Flow Methods
1 Payback Period measures:
A. The time value of money
B. The time taken to recover the initial investment
C. The firm's WACC
D. The tax liability of a project
E. The bond's duration
Answer: B. Payback measures time to recover the initial outlay.
2 Payback Period ignores:
A. The initial investment amount
B. The time value of money and cash flows beyond the payback point
C. The annual cash inflow
D. All cash flows entirely
E. The project's name
Answer: B. Payback ignores time value and post-payback cash flows.
3 ARR is based on:
A. Discounted cash flows
B. Accounting profit, not cash flow
C. Only tax figures
D. Market capitalisation
E. Bond duration
Answer: B. ARR uses accounting profit.
4 ARR is calculated as:
A. Average Annual Profit ÷ Average Investment × 100
B. Initial Investment ÷ Annual Cash Inflow
C. NPV ÷ Initial Investment
D. PV of Inflows − Initial Investment
E. IRR − Cost of Capital
Answer: A. ARR = Average Annual Profit ÷ Average Investment × 100.
5 Both Payback Period and ARR are classified as:
A. Discounted Cash Flow methods
B. Non-discounted (traditional) methods
C. Bond valuation methods
D. Ratio Analysis methods
E. Tax computation methods
Answer: B. Both are non-discounted/traditional methods.
💹 Discounted Cash Flow Methods
6 NPV is calculated as:
A. PV of cash inflows minus initial investment
B. Initial investment minus PV of cash inflows
C. Average profit divided by investment
D. Cash inflow divided by investment
E. Investment multiplied by tax rate
Answer: A. NPV = PV of inflows − initial investment.
7 A project should be accepted under NPV if:
A. NPV < 0
B. NPV > 0
C. NPV = Initial Investment
D. NPV is undefined
E. NPV equals the tax rate
Answer: B. Accept if NPV > 0.
8 IRR is defined as the discount rate at which:
A. NPV equals zero
B. NPV is maximised
C. Payback equals zero
D. ARR equals 100%
E. Tax liability is zero
Answer: A. IRR is the rate at which NPV = 0.
9 A project should be accepted under IRR if:
A. IRR is less than the cost of capital
B. IRR exceeds the cost of capital/hurdle rate
C. IRR equals zero
D. IRR is undefined
E. IRR equals the tax rate
Answer: B. Accept if IRR exceeds the hurdle rate.
10 The Profitability Index (PI) is calculated as:
A. PV of Cash Inflows ÷ Initial Investment
B. Initial Investment ÷ PV of Cash Inflows
C. NPV × Initial Investment
D. IRR ÷ Cost of Capital
E. Payback ÷ Project Life
Answer: A. PI = PV of Cash Inflows ÷ Initial Investment.
11 A project should be accepted under PI if:
A. PI < 1
B. PI > 1
C. PI = 0
D. PI is negative
E. PI equals the tax rate
Answer: B. Accept if PI > 1.
12 PI is particularly useful for:
A. Ranking projects under capital rationing
B. Computing tax liability
C. Calculating bond duration
D. Setting the repo rate
E. Computing forex cross rates
Answer: A. PI helps rank projects under capital rationing.
⚖️ Comparing NPV and IRR
13 NPV assumes interim cash flows are reinvested at:
A. The IRR
B. The cost of capital
C. Zero
D. The tax rate
E. The repo rate always
Answer: B. NPV assumes reinvestment at the cost of capital.
14 IRR assumes interim cash flows are reinvested at:
A. The cost of capital
B. The IRR itself
C. Zero
D. The GST rate
E. The forward rate
Answer: B. IRR assumes reinvestment at the IRR itself.
15 For mutually exclusive projects with conflicting NPV/IRR rankings, the generally preferred method is:
A. IRR
B. NPV
C. Payback Period
D. ARR
E. None; both are equally reliable always
Answer: B. NPV is generally preferred in conflicts.
16 Non-conventional cash flows (multiple sign changes) can cause IRR to:
A. Always give one clear, unambiguous answer
B. Yield multiple or no real solutions
C. Equal exactly the cost of capital always
D. Become identical to NPV always
E. Have no effect on IRR at all
Answer: B. Non-conventional cash flows can give multiple/no IRR solutions.
17 NPV's reinvestment assumption is generally considered:
A. Less realistic than IRR's
B. More realistic than IRR's
C. Identical to IRR's in every case
D. Irrelevant to project evaluation
E. Applicable only to bonds
Answer: B. NPV's assumption is generally more realistic.
🏗️ Basic Concepts of Term Loans
18 A Term Loan is typically used to finance:
A. Day-to-day working capital only
B. Capital expenditure or a project
C. Only foreign travel
D. Only tax payments
E. Only dividend payments
Answer: B. Term loans finance capex/projects.
19 The key appraisal metric for a term loan's repayment capacity is:
A. Current Ratio
B. DSCR
C. GST rate
D. Bond Duration
E. Current Yield
Answer: B. DSCR is the key term-loan repayment metric.
20 A "moratorium period" in a term loan refers to:
A. A period before regular repayment begins
B. Permanent waiver of the entire loan
C. A period of zero interest accrual
D. The final instalment only
E. A tax exemption period
Answer: A. Moratorium is the period before regular repayment starts.
21 Term loans are repaid through:
A. A fixed instalment schedule from future cash accruals
B. Immediate lump-sum repayment always
C. Sale of the borrower's current assets only
D. No repayment ever
E. Forgiveness after 1 year
Answer: A. Term loans repay via fixed instalments from cash accruals.
22 Term loan tenure is typically:
A. Less than 1 year always
B. Beyond 1 year
C. Exactly 1 day
D. Unlimited, with no fixed tenure
E. Only 1 week
Answer: B. Term loans have tenure beyond 1 year.
🤝 Deferred Payment Guarantee (DPG)
23 A DPG is issued by a bank on behalf of a:
A. Seller, to guarantee delivery of goods
B. Buyer, to guarantee payment of deferred instalments
C. Government, for tax collection
D. Notary Public
E. RBI, for monetary policy
Answer: B. DPG guarantees a buyer's deferred payment.
24 A DPG is structured on the bank's books as:
A. A direct fund-based loan
B. A contingent liability (guarantee)
C. A fixed deposit
D. Share capital
E. A bond investment
Answer: B. DPG is a contingent liability/guarantee.
25 The bank's income from a DPG is primarily:
A. Interest income
B. Commission
C. Dividend income
D. Capital gains
E. Rent
Answer: B. DPG income is commission-based.
26 DPGs are especially common for financing:
A. Machinery purchases
B. Daily grocery expenses
C. Personal travel
D. Tax payments
E. Dividend distribution
Answer: A. DPGs commonly finance machinery purchases.
27 A DPG functions economically like a:
A. Term loan, but structured as a guarantee
B. Savings account
C. Equity investment
D. Cheque book facility
E. Fixed deposit
Answer: A. A DPG functions like a term loan, structured as a guarantee.
🏭 Project Financing
28 Project Financing is structured around:
A. The sponsor's overall balance sheet
B. The cash flows and assets of a specific project
C. The government's tax revenue
D. Only equity capital
E. The RBI's balance sheet
Answer: B. Project Financing is structured around a specific project's cash flows.
29 Project Financing is often executed via a:
A. Special Purpose Vehicle (SPV)
B. Sole proprietorship only
C. Cooperative society only
D. Government department directly
E. Individual retail account
Answer: A. An SPV is the typical vehicle for project financing.
30 "Non-recourse" or "limited-recourse" financing means the lender's recourse is:
A. Unlimited against the sponsor's entire assets
B. Limited mainly to the project's own assets and cash flows
C. Against the government treasury
D. Against the RBI
E. Zero, with no recourse of any kind
Answer: B. Recourse is limited mainly to the project itself.
31 Project Financing is the dominant structure for:
A. Small retail personal loans
B. Large infrastructure projects like roads and power plants
C. Credit card transactions
D. Savings accounts
E. Fixed deposits
Answer: B. Project financing dominates large infrastructure projects.
32 A key risk in project financing that lenders scrutinise closely is:
A. The project's own future cash-generating ability
B. Only the sponsor's unrelated personal wealth
C. Only the government's tax policy
D. Only the RBI's monetary policy
E. No risk exists in project financing
Answer: A. The project's own cash-generating ability is closely scrutinised.
⚖️ Term Loan Appraisal vs Project Appraisal
33 Term Loan Appraisal is typically applied to:
A. A brand-new Greenfield venture with no track record
B. An existing, operational business seeking capex/expansion finance
C. A government department only
D. Personal consumption loans only
E. Savings account holders only
Answer: B. Term Loan Appraisal applies to existing operational businesses.
34 Project Appraisal for a Greenfield venture relies mainly on:
A. The sponsor's existing operating track record
B. Projections, since there is no existing track record
C. Only historical financial statements
D. No analysis at all
E. Only the borrower's personal credit score
Answer: B. Project Appraisal relies on projections, absent a track record.
35 Project Appraisal typically studies feasibility across: (i) Technical (ii) Market (iii) Managerial
A. (i) only
B. (i) and (ii) only
C. (iii) only
D. All of (i), (ii) and (iii)
E. None of these
Answer: D. All three feasibility dimensions are studied.
36 Compared to Term Loan Appraisal, Project Appraisal is generally:
A. Less rigorous
B. More comprehensive and rigorous
C. Identical in scope
D. Not required at all
E. Based solely on the borrower's age
Answer: B. Project Appraisal is more comprehensive and rigorous.
37 Term Loan Appraisal focuses primarily on:
A. Incremental project cash flows layered on existing operations
B. Only the promoter's personal assets
C. Only government subsidies
D. Only foreign exchange reserves
E. Only the RBI's repo rate
Answer: A. It focuses on incremental cash flows on top of existing operations.
🔁 Comprehensive Review
38 Which method would be most appropriate for ranking two mutually exclusive projects of different sizes under limited capital?
A. Payback Period alone
B. Profitability Index (PI)
C. ARR alone
D. No method is appropriate
E. Bond Duration
Answer: B. PI is well-suited for ranking under capital rationing.
39 A project with NPV = 0 implies:
A. The project earns exactly the cost of capital, no more, no less
B. The project is definitely unprofitable
C. The project should never be considered
D. The IRR is undefined
E. The Payback Period is infinite
Answer: A. NPV = 0 means the project earns exactly the cost of capital.
40 A shorter Payback Period is generally seen as:
A. Riskier and less desirable
B. Less risky and generally preferable, all else equal
C. Completely irrelevant to risk
D. Always inferior to a longer payback
E. Unrelated to liquidity
Answer: B. A shorter payback is generally less risky, preferable.
41 A bank appraising a Greenfield infrastructure SPV would place the greatest emphasis on:
A. The SPV's non-existent past financial statements
B. Rigorous technical, market and financial feasibility of the project itself
C. Only the sponsor's unrelated business interests
D. Only the RBI's repo rate
E. Only the borrower's personal credit card history
Answer: B. Rigorous project feasibility is the key focus for Greenfield SPVs.
42 Compared to a fund-based term loan, a DPG:
A. Involves an immediate cash outflow by the bank at sanction
B. Does not involve an immediate cash outflow, since it is a guarantee
C. Is identical in every respect to a term loan
D. Cannot be used for machinery purchase
E. Always earns interest, never commission
Answer: B. A DPG doesn't involve immediate cash outflow, being a guarantee.
43 Discounted cash flow methods are considered superior to non-discounted methods primarily because they:
A. Ignore the time value of money entirely
B. Account for the time value of money
C. Are easier to calculate without any data
D. Never require a discount rate
E. Are identical to Payback Period
Answer: B. DCF methods account for the time value of money.
44 If a project's IRR exceeds the firm's WACC, the project's NPV (at WACC as the discount rate) will typically be:
A. Negative
B. Positive
C. Exactly zero always
D. Undefined
E. Unrelated to IRR
Answer: B. IRR above WACC generally implies positive NPV.
45 A project financing lender relies principally on which source of repayment?
A. The project's own future cash flows
B. The sponsor's unrelated personal assets exclusively
C. Government bailout guaranteed in advance
D. RBI's direct funding
E. No repayment source is analysed
Answer: A. The project's own future cash flows are the primary repayment source.
46 Payback Period is often used alongside NPV/IRR primarily to assess:
A. Liquidity risk — how quickly funds are recovered
B. Long-term profitability alone
C. Tax liability
D. GST computation
E. Bond duration
Answer: A. Payback supplements DCF methods by highlighting liquidity/risk.
47 A bank guarantee's underlying nature as a "contingent" liability means:
A. The bank pays out only if the guaranteed party defaults
B. The bank always pays immediately upon issuance
C. No liability exists at all
D. The guarantee is identical to a fixed deposit
E. The buyer bears zero obligation
Answer: A. A contingent liability triggers payment only on default.
48 Between two projects with equal initial investment but different cash flow timing, NPV correctly captures the difference because it:
A. Ignores the timing of cash flows entirely
B. Discounts cash flows to reflect when they actually occur
C. Only considers the final year's cash flow
D. Uses accounting profit instead of cash flow
E. Has no relation to cash flow timing
Answer: B. NPV discounts cash flows based on actual timing.
49 For a bank, understanding whether a proposal is a "Term Loan" or a genuine "Project Finance" case matters because it affects:
A. The depth and nature of appraisal required
B. Nothing; both are appraised identically in every respect
C. Only the borrower's dress code
D. Only the branch location
E. Only the currency of the loan
Answer: A. The classification affects the depth/nature of appraisal.
50 For JAIIB purposes, the single most important reason NPV is favoured over ARR/Payback in modern capital budgeting is:
A. NPV incorporates the time value of money and all relevant cash flows
B. NPV is simpler to calculate by hand
C. NPV ignores risk entirely, which is desirable
D. ARR is always more accurate
E. Payback Period considers every future cash flow
Answer: A. NPV's time-value and full-cash-flow treatment is the key advantage.
Disclaimer: This article is prepared for educational and exam-preparation purposes only, as of September 2026. Candidates should cross-check the latest official IIBF syllabus and current notifications before the exam.